Oracle’s AI Project Faces Delivery Test as Market Reassesses “Stargate” Prospects

AI浪潮助推甲骨文云业务,分析师大幅上调甲骨文目标价
Published on: Sep 24, 2026
Author: Amy Liu

Oracle Corporation’s (ORCL) AI computing infrastructure expansion is facing multiple challenges ranging from energy supply and engineering delivery to contractual liability and credit pricing. Its large data center project in New Mexico, Project Jupiter, may not be able to begin operations as planned in 2028 due to permitting obstacles for its supporting natural gas pipeline. Oracle has issued a force majeure notice to a company under project developer Blue Owl Capital, hoping to delay payments. The company stated that it is not withdrawing from its role as the primary tenant, but rather seeking payment flexibility for a potential delay, and reiterated that the project is progressing according to the established schedule.

Energy and Permitting Become Key Bottlenecks

Project Jupiter is designed for a power usage scale of 2.45 gigawatts and plans to rely on Bloom Energy’s natural gas fuel cells for power supply. However, the New Mexico State Land Office has once again rejected the relevant pipeline route application, and the commissioning time for the supporting pipeline has been postponed to February 1, 2027. From the perspective of data center engineering economics, between signing computing power orders and delivering billable computing capacity on schedule, there remain stages including fuel supply, power supply reliability, environmental permitting, and system acceptance. Any delay could widen the gap between upfront investment and subsequent revenue realization.

Financing Structure Amplifies Timing Gap Risk

The project is being developed by Stack Infrastructure under Blue Owl Capital, with approximately 20 banks providing US$18 billion in project loans. Oracle, as the primary tenant, is taking on the campus capacity to serve downstream computing demand including that of OpenAI. If Oracle successfully delays payments, the developer’s cash recovery may be pushed back, but construction expenditures and financing obligations may not necessarily pause in tandem. Legal analysis emphasizes that force majeure relief depends on specific contract terms, and a performance grace period under one contract will not automatically cover other financing or power supply contracts. The market has already reacted, with debt prices related to the project development falling below 90 cents per US$1 of face value.

Huge Orders but Cash Flow Under Pressure

Oracle’s cloud infrastructure business revenue grew 121% year over year, with remaining performance obligations reaching US$664 billion, but only about 13% is expected to be recognized as revenue in the next 12 months. Capital expenditure in the latest quarter reached US$28.499 billion, exceeding operating cash flow, with free cash flow at negative US$5.396 billion. The book balance of borrowings is approximately US$125.337 billion, not yet including all lease obligations. The credit market has already become more vigilant, with S&P downgrading its rating to BBB−, and the five-year credit default swap spread previously rising to 215 basis points.

Summary

The delivery outlook for Project Jupiter is becoming a key test of the quality of Oracle’s AI expansion. The market’s doubts about Oracle’s “AI bubble” will ultimately need to be answered with on-schedule delivery, sustained cash collection, and leverage improvement. The project has turned issues originally hidden in long-term growth forecasts into observable engineering and contractual milestones. If delays push revenue back while construction and financing expenditures continue, even if long-term orders do not disappear, the project’s return on capital may decline, and new financing may require paying a higher risk premium.